FP245
Green City Kigali: a new model for urban development in Rwanda
Green City Kigali: a new model for urban development in Rwanda
As Rwanda urbanises rapidly, it is facing significant climate variability, which is leading to increased heat and more erratic and heavy precipitation. The resulting floods and landslides in informal peri-urban expansion areas around the capital city Kigali recurrently lead to the destruction of homes, infrastructure, livelihoods, and the loss of lives.
The Government of Rwanda is committed to addressing these climate challenges facing large parts of its urban population by changing the paradigm of public investments. The Green City Kigali Masterplan for Kinyinya Hill sets out a complete settlement with climate risk-reducing infrastructure and decentralised low-carbon basic services. On-site vocational training will enable the community to upskill and partake in the green transformation, building sustainable and resilient livelihoods.
The Green City Kigali Project will allow Rwanda to implement this changing paradigm and invest comprehensively in climate-compatible upgrading. This will build climate resilience for the existing community and new residents. The project aims to make recurrent flooding, landslides, and loss of livelihoods and lives a thing of the past.
The funding proposal was developed with support provided by the Project Preparation Facility.
Project timeline
Pipeline
30 Jun 2017 - 2674 days
Concept note received
30 Jun 2017
Funding proposal received
25 May 2023
Cleared by iTAP
21 Oct 2024
Approved
24 Oct 2024 - 180 days
Approved by GCF Board
24 Oct 2024
FAA executed
24 Oct 2024
Under implementation
21 Apr 2025 - -171 days so far
FAA effective
21 Apr 2025
To be completed
21 Apr 2030 - 1,998 days to go
-
Financing
- Private sector
- Public sector
-
Size
- Micro
- Small
- Medium
- Large
GCF financing
Instrument | Amount |
---|---|
Grant | USD 27,995,786 |
Total GCF Financing |
---|
USD 27,995,786 |
Co-financing
Co-financer | Instrument | Amount |
---|---|---|
Co-Financing | In-kind | USD 7,111,989 |
Total Co-Financing |
---|
USD 7,111,989 |
GCF Contacts
General media inquiries
GCF CommunicationsSend e-mail
Request for information
GCF Information DisclosureRequest information about this project
Project complaints and grievances
GCF Independent Redress Mechanism (IRM)Phone +82 32 458 6186 (KST)
File a complaint
Integrity issues
GCF Independent Integrity Unity (IIU)Phone +82 32 458 6714 (KST)
Send e-mail
Entity
Ministry of Environment (formerly Ministry of Natural Resources of Rwanda)
Permanent Secretary
Nyarugenge Pension Plaza, KN 3rd Road,, Kigali, Rwanda
More contacts
National Designated Authority
Rwanda Environment Management Authority
Director General